Trevors build 12

The transmission tower is now complete and was done pretty well to plan. Again keeping things accurate with hole centers and the like is key to getting a good build. I was able to weld it all myself  but getting it done at a fab shop would be no problem.  It has been tried in the duct and the next job is the support wings and deflector plates.  After a long wait I finally got my fan from Wingfan. It was good to mount it in the duct and see it spin with minimal clearance.

IMG_20210130_152931-8.jpg IMG_20210115_165220-7.jpg IMG_20210111_114743-5.jpg IMG_20210112_121523-6.jpg IMG_20210111_114731-4.jpg IMG_20210111_114708-2.jpg IMG_20210111_114725-3.jpg IMG_20210104_153030-0.jpg IMG_20210104_173148-1.jpg